Multiple Choice
A milestone is a typical measuring point used when establishing cost control.Which of the following does NOT accurately describes the use of cost control milestones?
A) Project managers can use their cash flow projections to determine the funding needed to reach each milestone.
B) Project managers and sponsors often decide the number of milestones jointly.
C) Milestones are often identified in the project charter.
D) Milestones are developed during risk planning.
Correct Answer:

Verified
Correct Answer:
Verified
Q19: "Unknown unknowns" are unexpected events which can
Q20: Generally,parametric estimating requires less information and time
Q21: All of the following items describe an
Q22: Early in a project when very little
Q23: Cost estimating is linked very closely with
Q25: Which of the following terms best describes
Q26: A project manager needs to ensure that
Q27: Typically,expedited costs are preferred over regular costs.
Q28: Regardless of what method is used to
Q29: Costs that repeat as project work continues