Multiple Choice
All of the following items describe an aspect of life cycle costing EXCEPT:
A) Life cycle cost includes the cost of both creating the project and of using the result of the project during its useful life.
B) Many project selection decisions are made based upon life cycle cost.
C) Life cycle cost only includes the project cost from initiating through closing
D) Project managers may need to consider disposal costs of the product after its useful life is complete to calculate total life cycle cost.
Correct Answer:

Verified
Correct Answer:
Verified
Q16: The _is the approved budget,usually in a
Q17: The component of the project management plan
Q18: Plan Cost Management is the process to
Q19: "Unknown unknowns" are unexpected events which can
Q20: Generally,parametric estimating requires less information and time
Q22: Early in a project when very little
Q23: Cost estimating is linked very closely with
Q24: A milestone is a typical measuring point
Q25: Which of the following terms best describes
Q26: A project manager needs to ensure that