Multiple Choice
Some organizations rely upon a formal group authorized and responsible for reviewing,evaluating,approving,delaying,or rejecting any changes to any aspect of the project plan by following a formal communication method of documenting the decision process.This group is typically known as a:
A) stakeholder review board.
B) change control board.
C) project evaluation committee.
D) steering committee
Correct Answer:

Verified
Correct Answer:
Verified