Your Most Recent Project Performance Report Indicates That Your Cumulative

Question 21

Essay

Your most recent project performance report indicates that your cumulative Schedule Performance Index (SPI)is .85 and your cumulative Cost Performance Index (CPI)is .90.What conclusions can you draw from these performance indices? What actions might you take to address project performance based on these results?