Multiple Choice
During schedule and cost control,when comparing performance to the schedule and cost baselines,if schedule or budget has changed these changes should be:
A) formally recommended and managed through the integrated change control system
B) added to the original baselines, and baseline changes made to reflect the new status
C) reviewed with the customer or sponsor to obtain approval for additional funding
D) implemented immediately and reported as variances from baseline in the next status report
Correct Answer:

Verified
Correct Answer:
Verified
Q30: Describe the three different categories of risk
Q31: Which of the following measures is best
Q32: This is the process of reviewing all
Q33: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 14.1 Drug
Q34: When using earned value techniques,Actual Cost (AC)refers
Q36: Quality control charts are helpful in answering
Q37: Work to be performed can come from
Q38: Which of these is NOT one of
Q39: Some scope changes start as proposed changes
Q40: When project managers authorize work,they should empower