Multiple Choice
Work to be performed can come from the work package level of the work breakdown structure as well as other sources.Which of these is NOT a source of authorized work to be performed?
A) Corrective actions
B) Preventive actions
C) Scope creep
D) Defect repairs
Correct Answer:

Verified
Correct Answer:
Verified