For a Project with Uncertain Activity Times, the Probability of Project

Question 33

Multiple Choice

For a project with uncertain activity times, the probability of project completion exceeding the expected time calculated for the critical path is ________.


A) 25 percent
B) 50 percent
C) 75 percent
D) None of these answers are correct.

Correct Answer: