The Beta distribution is useful in network analysis because it ________.
A) provides formulas for calculating the activity mean and variance
B) can be approximated by a normal distribution
C) provides probability estimates for project completion time
D) requires only three time estimates to describe uncertain activity duration
Correct Answer:

Verified
Correct Answer: