Multiple Choice
A key assumption underlying project networks is: ________.
A) dummy activities take up no time
B) the critical path is known with certainty
C) an activity begins only after all predecessors are completed
D) a project network is cyclic
Correct Answer:

Verified
Correct Answer:
Verified