Multiple Choice
Which of the following is not considered a source of variance on the earned value chart?
A) Time.
B) Cost.
C) Schedule.
D) None of these answers are correct.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q14: Time variance is calculated by subtracting actual
Q15: Monte Carlo simulation of project networks is
Q16: Which of the following attributes is not
Q17: A major flaw in critical path analysis
Q18: Gantt charts fail to indicate the interdependence
Q20: Projects are terminated for all of the
Q21: The critical path for a project with
Q22: A key assumption underlying project networks is:
Q23: The four sequential stages of team development
Q24: A major assumption in project network analysis