    Which of the Following Is Not a Critical Time Estimate
Solved

Which of the Following Is Not a Critical Time Estimate

Question 3

Question 3

Multiple Choice

Which of the following is not a critical time estimate for a Beta distribution?


A) Optimistic time.
B) Pessimistic time.
C) Most likely time.
D) Expected time.

Correct Answer:

verifed

Verified

Related Questions

Q1: Schedule variance is the difference between budgeted

Q2: The critical path refers to the sequence

Q4: The term 'late finish' refers to the

Q5: A project can be defined as a

Q6: Total slack for an activity can be

Q7: When delays occur owing to technical difficulties,

Q8: Gantt project charts are useful for all

Q9: Which of the following is not true

Q10: Estimates of project expected completion time and

Q11: Developing a project network is the only

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines