Multiple Choice
If a system is being updated due to operating necessity,the project was selected because__________.
A) the system is worth saving at any cost
B) the system is worth saving at the estimated cost of the project
C) the dimension of cost is not relevant to execution of the project
D) the cost overruns can be hidden in someone else's budget
Correct Answer:

Verified
Correct Answer:
Verified