Multiple Choice
A project has four criteria,represented by A-D.There weights are 0.1,0.2,0.4,and 0.3.A particular project has scores of 4,5,8,and 9 respectively.What is its total score for the project?
A) 6.5
B) 7.1
C) 7.3
D) 26