Using the Power-Interest Grid,match up these two dimensions of stakeholders with the appropriate relationship with the project manager.
A)Low power,low interest
B)High power,low interest
C)High interest,low power
D)High interest,high power
1)Monitor
2)Keep informed
3)Closely manage
4)Keep satisfied
Correct Answer:

Verified
Correct Answer:
Verified