Multiple Choice
Planning a project should result in a number of outputs.Which of the following is not one of those outcomes?
A) Technical scope is established
B) Basic areas of performance responsibility are accepted by the participants
C) Every possible risk is identified and a contingency plan is developed
D) Any tentative delivery dates or budgets and their tolerances set by the parent organization are clearly noted