Multiple Choice
Unfortunately,it is all too common for projects to go over budget and / or be completed late.What is the main reason?
A) An improperly constructed WBS
B) Too much scope creep
C) An unplanned for risk event
D) Insufficient upfront planning
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q33: The _ of a project includes the
Q34: _ is the tendency for the project
Q35: Once the project charter is completed and
Q36: Describe how a risk management plan is
Q37: The _is a list of the project
Q39: During initial project planning,activities are identified and
Q40: The success of the project launch meeting
Q41: The process of coordinating the work and
Q42: Planning a project should result in a
Q43: This project plan element describes both the