    A Project Manager Must ______ as a Type of Risk
Solved

A Project Manager Must ______ as a Type of Risk

Question 55

Question 55

Multiple Choice

A project manager must ______ as a type of risk response planning in order to soften the danger of a threat by reducing the likelihood that it will occur or by reducing its impact if it does occur.


A) avoid
B) transfer
C) accept
D) mitigate

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q45: _ issues are present when bidders "low

Q46: The allowance for contingencies is usually in

Q47: Overhead costs are all of the following

Q48: _ costs are not associated with any

Q49: The pattern of deviations in cost and

Q50: Which of the following is not a

Q51: In risk response planning,where the goal of

Q52: The traditional organizational budget is _.<br>A)category-oriented<br>B)project-oriented<br>C)program-oriented<br>D)project-oriented or

Q53: Suggest some reasons why the authors insist

Q54: Suggest some reasons why an organization would

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines