The use of PERT has declined sharply in recent years because a large majority of project management software __________.
A) have become obsolete
B) use probabilistic techniques
C) generate CPM networks
D) are characterized by high prices
Correct Answer:

Verified
Correct Answer:
Verified
Q35: The basic approach of all scheduling techniques
Q36: In application,program evaluation and review technique (PERT)has
Q37: In AON diagrams,a(n)_ is a point where
Q38: Explain why it is important to evaluate
Q39: The series of connected activities (or intermediate
Q41: Project completion probabilities computed using just the
Q42: It is important to good project management
Q43: The authors define _ as the time
Q44: A precedence relationship where the completion of