Multiple Choice
A project has three paths and a desired completion time of 43 days.The first path has a 70 percent probability of being completed in 43 days.The second has an 85 percent probability and the third haws a 90 percent probability.What is the probability that the project will be completed on time?
A) 53.55 percent
B) 70 percent
C) 90 percent
D) 99.55 percent
Correct Answer:

Verified
Correct Answer:
Verified
Q44: A precedence relationship where the completion of
Q45: A precedent relationship where the completion of
Q46: A _ is a combination of interrelated
Q47: Which of the following is not a
Q48: The line connecting two nodes is referred
Q50: _ was developed by the U.S.Navy while
Q51: When using the beta distribution,the denominator of
Q52: Explain why completion probabilities computed using the
Q53: The calculation of the standard deviation for
Q54: A(n)_ is the conversion of the project