Solved

A Project Has Three Paths and a Desired Completion Time

Question 49

Multiple Choice

A project has three paths and a desired completion time of 43 days.The first path has a 70 percent probability of being completed in 43 days.The second has an 85 percent probability and the third haws a 90 percent probability.What is the probability that the project will be completed on time?


A) 53.55 percent
B) 70 percent
C) 90 percent
D) 99.55 percent