Multiple Choice
A clearly identifiable point in a project or set of activities that commonly denotes a reporting requirement or completion of a large or important set of activities is called a(n) __________.
A) milestone
B) anniversary
C) node
D) dummy activity
Correct Answer:

Verified
Correct Answer:
Verified