Multiple Choice
When crashing a project,our first task is to develop __________.
A) a table or graph of the cost of a project as a function of the project's possible completion dates
B) a schedule that shows the risks associated with each activity in the project
C) a list that shows the activities and the events of a project without referring to the costs
D) a table showing the noncritical activities and the cost associated with each of those activities