Multiple Choice
Using Goldratt's meaning of the word "dependent," the activities of a project can be ordered into paths based on their resource dependencies as well as on their technological precedence requirements.The longest of these paths of sequentially time-dependent activities is known as the ______________.
A) priority chain
B) critical chain
C) dependency path
D) heuristic path
Correct Answer:

Verified
Correct Answer:
Verified