Multiple Choice
In earned value Analysis,the 50-50 rule assumes that __________.
A) 50 percent is earned when the task is half done and 50 percent is earned at completion
B) 50 percent is earned when the task begins and 50 percent is earned at completion
C) 50 percent is earned when the task begins and 50 percent is earned at the halfway stage
D) 50 percent is earned when the project is planned and 50 percent is earned when the project is over
Correct Answer:

Verified
Correct Answer:
Verified
Q43: Describe the three common difficulties in designing
Q44: What is the most likely project report
Q45: For project management,there are three distinct types
Q46: If EV = $500,AC = $475,PV =
Q47: Which of the following conventions has the
Q48: Monitoring,as an activity,should be kept distinct from
Q49: The best sources of items to be
Q50: Conceptually,EAC represents the amount spent to date
Q51: Monitoring,as an activity,should be kept distinct from
Q53: The most common mistake made when monitoring