Multiple Choice
Which of the following conventions has the characteristic of the project always seeming to be running late,until the very end when it seems to suddenly catch up?
A) The 50-50 rule
B) The 0-100 percent rule
C) Critical input use rule
D) The proportionality rule
Correct Answer:

Verified
Correct Answer:
Verified