In Earned Value Analysis,if the Cost Variance Is (-$10,000),__________

Question 23

Multiple Choice

In earned value analysis,if the cost variance is (-$10,000) ,__________.


A) the cost variance is favorable
B) the cost variance is unfavorable
C) the scheduled variance is favorable
D) the scheduled cost avoidance is unfavorable