Multiple Choice
In earned value analysis,if the cost variance is (-$10,000) ,__________.
A) the cost variance is favorable
B) the cost variance is unfavorable
C) the scheduled variance is favorable
D) the scheduled cost avoidance is unfavorable
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q18: If EV = $500,AC = $475,PV =
Q19: ETC + AC = _.<br>A)BAC<br>B)EAC<br>C)SPI<br>D)CPI
Q20: ST-AT =<br>A)TV<br>B)EV<br>C)CV<br>D)SV
Q21: Vague or incomplete project requirements are an
Q22: Unfortunately,it is common to focus monitoring activities
Q24: The earned value rule that divides the
Q25: (BAC + EV) / CPI = _.<br>A)EAC<br>B)TPI<br>C)CPI<br>D)ETC
Q26: According to the authors,the key items to
Q27: A status report that is vague or
Q28: If EV = $500,AC = $450,PV =