Multiple Choice
Vague or incomplete project requirements are an example of which telltale sign that a project is in trouble?
A) Muddy waters
B) Mysterious stakeholders
C) Unconstrained constraints
D) Scope creep
Correct Answer:

Verified
Correct Answer:
Verified