Multiple Choice
A meeting place for the project team,a display area for the charts that show the project's progress,a central repository for project files and reports,and an office for the project management and other project administrators.
A) Project office
B) Project conference room
C) War room
D) Project club house
Correct Answer:

Verified
Correct Answer: