Multiple Choice
In the future project status of the audit report,no assumptions should be made about __________ that are still under investigation at the time of the audit.
A) financial problems
B) ethical problems
C) efficiency problems
D) technical problems
Correct Answer:

Verified
Correct Answer:
Verified