Multiple Choice
Projects that pass away simply because senior managers,the project champion,the PM,and even key project workers lose interest in the project are known as __________.
A) political closures
B) senescence closures
C) conflict closures
D) closures by addition
Correct Answer:

Verified
Correct Answer:
Verified