The Primary Criterion for Project __________ Is Whether or Not

Question 3

Multiple Choice

The primary criterion for project __________ is whether or not the organization is willing to invest the estimated time and cost required to complete the project,given the project's current status and current expected outcome.


A) continuance
B) closure
C) continuance or closure
D) extinction

Correct Answer:

verifed

Verified