Simple Project Listing of Five Activities,their Predecessors,and Their Respective Time

Question 66

Multiple Choice

simple project listing of five activities,their predecessors,and their respective time estimates are presented below:
simple project listing of five activities,their predecessors,and their respective time estimates are presented below:   Using CPM,what is the Latest Finish Time for the last activity in this project (i.e. ,the total time to complete the project) ? A) 10 days B) 7 days C) 8 days D) 12 days E) 9 days
Using CPM,what is the Latest Finish Time for the last activity in this project (i.e. ,the total time to complete the project) ?


A) 10 days
B) 7 days
C) 8 days
D) 12 days
E) 9 days