Multiple Choice
simple project listing of five activities,their predecessors,and their respective time estimates are presented below:
Using CPM,what is the Latest Finish Time for the last activity in this project (i.e. ,the total time to complete the project) ?
A) 10 days
B) 7 days
C) 8 days
D) 12 days
E) 9 days
Correct Answer:

Verified
Correct Answer:
Verified
Q21: You are managing a project and need
Q24: In a project analysis using three time
Q44: Upper-level management must decide between pure, functional,
Q50: Complex projects are often subdivided into a
Q61: disadvantage of a matrix project organizational structure
Q63: The second step in managing a project
Q63: listing of immediate predecessor activities is important
Q68: You have the following time and cost
Q71: company must perform a maintenance project consisting
Q79: Slack activity time is the difference between