Company Must Perform a Maintenance Project Consisting of Seven Activities

Question 71

Multiple Choice

company must perform a maintenance project consisting of seven activities.The activities,their predecessors,and their respective time estimates are presented below:
company must perform a maintenance project consisting of seven activities.The activities,their predecessors,and their respective time estimates are presented below:   Using CPM,which activities make up the critical path? A) A,B,D,F,G B) A,C,E,F,G C) A,C,B,F,E D) A,D,E E) None of these
Using CPM,which activities make up the critical path?


A) A,B,D,F,G
B) A,C,E,F,G
C) A,C,B,F,E
D) A,D,E
E) None of these