Below are the data for a Time-Cost CPM Scheduling analysis.The time is in days and the costs include both direct and indirect costs.
If you crash this project to reduce the total time by four days,what is the total time of the project and total cost?
A) Total time is 10 days,total cost is $2500
B) Total time is 9 days,total cost is $2300
C) Total time is 8 days,total cost is $2750
D) Total time is 8 days,total cost is $1850
E) Total time is 9 days,total cost is $2350
Correct Answer:

Verified
Correct Answer:
Verified
Q9: A work breakdown structure is used in
Q11: A project may be defined as a
Q14: PERT is an abbreviation for which of
Q16: You have collected the data for a
Q17: simple project listing of five activities,their predecessors,and
Q53: You know when you have arrived at
Q57: What is a work breakdown structure?<br>A)A list
Q59: In the Time-Cost CPM model, cost is
Q72: The critical path in a CPM analysis
Q104: In CPM, the late start time estimate