Multiple Choice
You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project "direct costs" are given below.
The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200,and 13 days they will be $100.At what day do we achieve the lowest total project cost (i.e. ,direct plus indirect costs) ?
A) 16 days
B) 15 days
C) 14 days
D) 13 days
E) 12 days
Correct Answer:

Verified
Correct Answer:
Verified
Q11: A project may be defined as a
Q14: Below are the data for a Time-Cost
Q14: PERT is an abbreviation for which of
Q17: simple project listing of five activities,their predecessors,and
Q29: Earned Value Management (EVM) has the capability
Q56: What does "EVM" stand for?<br>A) Extra Value
Q57: What is a work breakdown structure?<br>A)A list
Q59: In the Time-Cost CPM model, cost is
Q72: The critical path in a CPM analysis
Q104: In CPM, the late start time estimate