In a Critical Path Network, Those Activities That Aren't on the Critical

Question 72

True/False

In a critical path network, those activities that aren't on the critical path typically have some slack, meaning that a delay in their completion is unlikely to create a delay in the completion of the overall project-as long as the delay isn't too great.