With the backyard poultry craze unleashing a tidal wave of municipal code proposals, Chickenverks is poised to capitalize on the sudden demand for chicken tractors. The portable henhouses they have designed can be assembled in 10 basic steps, each with a required time and predecessor as shown in the table. There are 8 productive hours available in a day and the manufacturer wishes to produce 40 units per hour.
 Task  Time (sec)  Predecessor  A 25 B 35 A  C 20 A  D 55 B  E 45 C, D  F 15 B  G 35 C  H 40 D, E  J 25 F, G  K 30 H, J \begin{array} { | c | c | c | } \hline \text { Task } & \text { Time } ( \mathrm { sec } ) & \text { Predecessor } \\\hline \text { A } & 25 & \cdots \\\hline \text { B } & 35 & \text { A } \\\hline \text { C } & 20 & \text { A } \\\hline \text { D } & 55 & \text { B } \\\hline \text { E } & 45 & \text { C, D } \\\hline \text { F } & 15 & \text { B } \\\hline \text { G } & 35 & \text { C } \\\hline \text { H } & 40 & \text { D, E } \\\hline \text { J } & 25 & \text { F, G } \\\hline \text { K } & 30 & \text { H, J } \\\hline\end{array}
-Refer to the scenario above. What is the theoretical minimum number of stations needed?


A) 3
B) 4
C) 5
D) 6

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions