Multiple Choice
There is no beginning inventory.What are the net requirements in week 4 if there is a scheduled receipt of 100 units each week and a two week production lead time?
A) 250
B) 300
C) 350
D) 400
Correct Answer:

Verified
Correct Answer:
Verified