Multiple Choice
A seven activity project has the activity durations (in weeks) and costs shown in the table.It is possible to speed up every one of the activities by paying a little more.What is the least expensive 30-week project?
A) $18,900
B) $19,200
C) $19,500
D) $19,800
Correct Answer:

Verified
Correct Answer:
Verified