Which of these needs does the Guide to the Project Management Body of Knowledge NOT serve?
A) It provides a common language for discussing project management issues.
B) It provides a blueprint for ISO certification of the project management process.
C) It identifies and disseminates generally accepted project management knowledge and practices.
D) It serves as a basic reference source for project management.
Correct Answer:

Verified
Correct Answer:
Verified
Q47: For critical path activities, slack is equal
Q48: The university president concocts a thirteen-step
Q49: Key points in a project, such as
Q50: Performance or time targets for each major
Q51: The university president concocts a thirteen-step
Q53: A hatmaker, fresh off a very
Q54: Construction of the cattery could be
Q55: What is the latest that activity D
Q56: A project is composed of 6
Q57: The tablet unearthed by the archaeologist