Question 7

Multiple Choice

A company uses 4 pounds of resource 1 to make each unit of X1 and 3 pounds of resource 1 to make each unit of X2. There are only 150 pounds of resource 1 available. Which of the following constraints reflects the relationship between X1, X2 and resource 1?


A) 4 X1 + 3 X2 \ge 150
B) 4 X1 + 3 X2 \le 150
C) 4 X1 + 3 X2 = 150
D) 4 X1 \le 150