Multiple Choice
A company wants to use PERT to manage a project. They have developed the following spreadsheet for the problem. If The Risk Solver Platform (RSP) is used, what formula should go in cell F3 of the spreadsheet to compute the Activity Time when simulating a PERT analysis?
A) =IF(E3 (C3-E3) /(D3-B3) ,D3-SQRT((D3-B3) *(D3-C3) *(1-E3) ) ,B3+SQRT((D3-E3) *(C3-B3) *E3) )
B) =IF(E3 0(D3-B3) /(C3-E3) ,B3+SQRT((D3-E3) *(C3-B3) *E3) ,D3-SQRT((D3-B3) *(D3-C3) *(1-E3) ) )
C) =IF(E3 (C3-E3) /(D3-B3) ,B3-SQRT((D3-E3) *(C3-B3) *E3) ,D3+SQRT((D3-B3) *(D3-C3) *(1-E3) ) )
D) =PsiTriangular(B3,C3,D3)
Correct Answer:

Verified
Correct Answer:
Verified
Q15: Exhibit 15.2<br>The following questions employ the AON
Q43: A company wants to use PERT to
Q44: <br>The following questions are based on the
Q45: <br>The following questions are based on the
Q45: Exhibit 15.1<br>The following questions employ the AON
Q46: How many paths are there in the
Q51: <br>The following questions are based on the
Q78: Exhibit 14.13<br>The following questions use the information
Q81: Exhibit 15.4<br>The following questions are based on
Q82: Exhibit 15.4<br>The following questions are based on