Essay
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
-Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?
Correct Answer:

Verified
Correct Answer:
Verified