Multiple Choice
A writer estimates it will take three months to generate spiffy documents to accompany a seminal work in operations management.He grossly underestimates the time required and misses his deadline by two months.This estimate was:
A) Objective and accurate.
B) Subjective and accurate.
C) Objective and inaccurate.
D) Subjective and inaccurate.
Correct Answer:

Verified
Correct Answer:
Verified