A company facing an interest rate of 8% must choose among projects offering the following four-year cash flows.If the company is employing the net present value criterion,which project should they choose?
A) $25,000 in year 1;$15,000 in year 2;$10,000 in year 3;and $5,000 in year 4
B) $5,000 in year 1;$5,000 in year 2;$20,000 in year 3;and $30,000 in year 4
C) $15,000 in year 1;$15,000 in year 2;$15,000 in year 3;and $15,000 in year 4
D) $5,000 in year 1;$5,000 in year 2;$25,000 in year 3;and $25,000 in year 4
Correct Answer:

Verified
Correct Answer:
Verified
Q36: What are the advantages and limitations of
Q37: A project manager is using the internal
Q38: A simplified scoring model addresses all the
Q39: Every decision model contains both objective and
Q40: The profile model plots a graph on
Q42: What is an internal rate of return
Q43: Successful firms use project portfolio planning routinely
Q44: Multiple project environments thrive on:<br>A)Multi-layered bureaucracy.<br>B)Rigid development
Q45: To see if a potential new project
Q46: A project that is exceptionally risky might