A Project That Is Exceptionally Risky Might Still Be Undertaken

Question 46

Multiple Choice

A project that is exceptionally risky might still be undertaken by a firm if they have several other projects underway that are considered more of a sure thing.This approach to project selection is BEST described by the criterion called:


A) Strategic "fit."
B) Risk.
C) Desire for portfolio balance.
D) Top management pressure.