Solved

A Project Manager Is Using the Net Present Value Method

Question 72

Multiple Choice

A project manager is using the net present value method to make the final decision on which project to undertake.The company has a 12% required rate of return and expects a 3% rate of inflation for the following four years.What is the NPV of a project that has cash flows as shown in the table?  Year  Cash Flow 0$250,0001$50,0002$60,0003$70,0004$80,000\begin{array} { | l | l | } \hline \text { Year } & \text { Cash Flow } \\\hline 0 & - \$ 250,000 \\\hline 1 & \$ 50,000 \\\hline 2 & \$ 60,000 \\\hline 3& \$ 70,000 \\\hline 4 & \$ 80,000 \\\hline\end{array}


A) -$9,762
B) -$56,859
C) -$69,387
D) -$98,780

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge