Multiple Choice
A project manager is using the net present value method to make the final decision on which project to undertake.The company has a 15% required rate of return and expects a 5% rate of inflation for the following four years.What is the NPV of a project that has cash flows as shown in the table?
A) $4.955
B) $42,586
C) -$23,667
D) -$122,569
Correct Answer:

Verified
Correct Answer: