A project manager is using the net present value method to make the final decision on which project to undertake.The company has a 15% required rate of return and expects a 5% rate of inflation for the following four years.What is the NPV of a project that has cash flows as shown in the table?  Year  Cash Flow 0$350,0001$50,0002$80,0003$100,0004$150,000\begin{array} { | l | l |} \hline \text { Year } & \text { Cash Flow } \\\hline 0 & - \$ 350,000 \\\hline 1 & \$ 50,000 \\\hline 2 & \$ 80,000 \\\hline 3 & \$ 100,000 \\\hline 4 & \$ 150,000 \\\hline\end{array}


A) $4.955
B) $42,586
C) -$23,667
D) -$122,569