Solved

A Project Manager Is Using the Payback Method to Make

Question 78

Multiple Choice

A project manager is using the payback method to make the final decision on which project to undertake.The company has a 10% required rate of return and expects a 4% rate of inflation for the following five years.What is the discounted payback of a project that has cash flows as shown in the table?  Year  Cash Flow 0$100,0001$20,0002$50,0003$50,0004$25,0005$500,000\begin{array} { | l | l | } \hline \text { Year } & \text { Cash Flow } \\\hline 0 & -\$ 100,000 \\\hline 1 & \$ 20,000 \\\hline 2 & \$ 50,000 \\\hline 3 & \$ 50,000 \\\hline 4 & \$ 25,000 \\\hline 5 & \$ 500,000 \\\hline\end{array}


A) 3.4 years
B) 2.6 years
C) 5.0 years
D) 4.2 years

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions