Multiple Choice
A project manager is estimating costs on her video game development project.She utilizes total costs from a similar project that was completed last year to estimate the costs on her current project.This is an example of:
A) Bottom-up estimation
B) Rough order magnitude estimation
C) Analogous estimation
D) Parametric estimation