A Project Manager Is Estimating Costs on Her Video Game

Question 65

Multiple Choice

A project manager is estimating costs on her video game development project.She utilizes total costs from a similar project that was completed last year to estimate the costs on her current project.This is an example of:


A) Bottom-up estimation
B) Rough order magnitude estimation
C) Analogous estimation
D) Parametric estimation

Correct Answer: