    Exam 8: Cost Estimation and Budgeting
  5. Question
    Rank the Four Different Types of Cost Estimates from Most
Solved

Rank the Four Different Types of Cost Estimates from Most

Question 64

Question 64

Essay

Rank the four different types of cost estimates from most to least accurate and explain what the inputs are to each type.

Correct Answer:

verifed

Verified

The cost estimates as ranked from most a...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q59: What are parametric cost estimates and how

Q60: Analogous estimation is a type of _

Q61: It took 66 hours of analysis to

Q62: Direct costs are those clearly assigned to

Q63: Estimates based on the assumption that historical

Q65: A project manager is estimating costs on

Q66: The term expedited cost has the same

Q67: An order of magnitude estimate is usually

Q68: What are function points and how do

Q69: The new artisanal greenhouse would require 700

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines